Leven Road

Location: E14
Duration: Potential 3 Year Project

Project Progress

The Leven Road project continues to progress in line with programme, with key electrical infrastructure milestones successfully achieved across the initial phases of the development.

To date, our team has completed the installation of primary electrical containment across 24 floors within the first three blocks, providing a robust and coordinated framework to support future electrical and ELV services. 

We have also been awarded the ground floor electrical containment scope, comprising approximately 2,500 metres of primary containment, further strengthening our role within the project delivery.

Next Project Stages

In preparation for the next stage, we have submitted a detailed commercial proposal covering the installation of:

  • Main and sub distribution boards
  • Automatic Transfer Switches (ATS)
  • Secondary containment systems
  • Small power and lighting installations
  • Fire detection and alarm systems
  • Security systems